This is the summary report of the
Liberty County Grand Jury whose term
of service was from February 12,
2006 to September 10, 2007. For
those unfamiliar with the full
duties of a grand jury in this
county, we wish to tell you that in
addition to the judgments that we
are obliged to make on whether the
County should proceed on with
further legal action on matters
concerning possible criminal
activity, we are also obliged to
report to you, the citizens of
Liberty County, on the performance
of four major governmental units
within our county whose purpose it
is to see to it that certain public
functions are carried out for your
benefit as effectively as possible
while doing so at the lowest
possible cost. We must also
entertain concerns from citizens of
this county who are able to present
meaningful arguments that the public
welfare of Liberty County is not
being properly served. The case of
Dr. Glenn Carter and the Liberty
County Hospital Authority is such a
case, and the issues raised by Dr.
Carter are discussed in this
presentment. Finally, because we
believe that it is our duty to
communicate our findings to the
citizens of Liberty County as
effectively as possible, in addition
to publishing our findings in our
local newspaper, The Coastal
Courier, we have also elected to
create a blogspot on the Internet to
make these findings available to
those who choose to review and
comment on the findings via
electronic media. We welcome all
responsible comments. The address of
the blogspot will be
http://libertycountygrandjury2007.blogspot.com/.
The governmental units involved
include the Liberty County Board
of Education, the Liberty County
Development Authority, the
Liberty Consolidated Planning
Commission, and the Liberty
County Board of Commissioners.
We invited those entities to
make presentations to us, and
they did so in shortly before or
in April 2007. What we received
from them, however, was
apparently something similar to
what they had presented to grand
juries in prior years. After
analyzing what we did receive,
we determined that all of those
agencies needed to submit
revised reports in a somewhat
standardized format designed to
help the next grand jury better
understand each agency’s
operation. It included the
following information:
-
A brief discussion of the
significant events of the
most recent business year
and the outlook for the
current year (construction
plans, staffing changes,
sources of funding, etc.).
-
A mission statement
outlining precisely what the
affected agency was charged
with doing along with a list
of its directors, their
current terms of service,
and their experience record
with the unit.
-
Sharply improved financial
information in a number of
areas. First, we asked them
to separate their operating
costs from their capital
costs so that we could see
just what it cost to operate
each agency each year, and
we also asked them to give
us that information for the
past two years plus the
current one so that we could
see what the trend looked
like for their operation. We
also asked each agency for
the compensation and
benefits paid to the two
most highly paid employees
on their staff. In effect,
we were saying that if your
top staff is sufficiently
well paid, we have a right
to expect solid financial
information from them. The
top staff members in all
agencies are sufficiently
well compensated to be held
responsible for being able
to produce meaningful annual
reports to this and all
future grand juries.
-
Finally, we asked for an in
depth discussion of each
major project that the
agency finished during the
past year, final contract
price information including
information about change
orders, contract
modifications, contract
completion dates, how the
project was financed, and
other matters that we
believed relevant to
assessing their performance.
The response to our
request was varied. One agency
responded within two weeks with a
report in a format which largely met
our concerns, while another stated
that they were an independent body,
our request for information was
highly irregular and certainly not
in keeping with what they had
submitted to previous grand juries,
and they were so busy with other
matters that they did not think that
it was possible to meet our request
for information in a timely manner.
While we were mindful of their
schedules, we reminded them that it
was our duty and the duty of all
future grand juries, as
representatives of the Liberty
County taxpayers, to make certain
that the affected agencies were
spending our tax dollars as wisely
as possible. In the end, we did
achieve during this term at least
partial compliance from all of the
agencies for which we were
responsible, and we report to you
our findings in this presentment.
Additionally, we hope that the
standard for reporting by those
agencies that we have developed
during our term will provide a
legacy for future grand juries.
Hopefully, the next grand jury will
receive far more revealing annual
performance reports than those with
which we initially received.
Our principal
findings on each agency follow, and
it is our hope that every citizen
and taxpayer in Liberty County will
read them in detail because it is
your tax dollar that is being spent,
and we believe that in a number of
cases it could be spent much more
wisely.
Findings:
Liberty County Board of Education (LCBE)
The Liberty County Board of
Education operates under the
authorization of an Act of the
legislature approved February 10,
1986, as amended. Its guidance is
provided by a board of directors
elected by the voters of Liberty
County, and its ongoing operation is
the responsibility of a
superintendent who is appointed by
that board. The board is a separate
legal entity and has the power to
levy taxes and issue bonds for its
needs. Its budget is not subject to
the approval of any other entity.
The Chairman of the Liberty County
Board of Education is Ms. Lily H.
Baker, and the Interim
Superintendent is Mr. Harley Grove.
The grand jury noted when reviewing
the audited LCBE financial
statements for the fiscal year ended
June 30, 2006 that it had on hand at
that time almost $50.7 million in
cash and cash equivalents,
investments, and related
receivables, while liabilities at
that time amounted to only about
$12.1 million. Further, it had no
long term debt at that time.
Effectively then, it had nearly
$38.6 million in virtually
unrestricted cash reserves.
Additionally, we noted that revenues
from all sources (excluding district
wide capital projects fund) exceeded
operating expenditures by
approximately $10.2 million in that
year, and barring a change of which
we are currently unaware, we see no
reason why we should not expect the
surplus of revenues over
expenditures to continue in future
years. Similar information for the
fiscal year ended June 30, 2007 is
not yet available, but we believe
that the Board’s cash reserves will
be even greater than at the end of
the previous year.
We are aware that it is always
prudent for an entity such as LCBE
to have a forward-looking capital
improvements plan, and, in fact,
they are required by Georgia Law
20-2-260 to develop and maintain a
long range comprehensive plan for
those needs that is updated every
five years if they are to
participate in state’s Capital
Outlay Program. In that regard, we
contacted LCBE concerning its
projected needs. That entity replied
that based upon information provided
by the state in connection with the
Capital Outlay Program, it did not
anticipate a drastic increase in
student population. It further added
that if the current trend holds
true, the school district will be
able to accommodate the projected
student population within its
current facilities. The Board went
on to say that, as a consequence, it
appears that the majority of its
capital spending should take the
form of renovations and
modifications to existing
facilities, and it provided us with
a list of projects which it plans to
undertake in the next five years.
None appear to be especially large
in dollar amounts.
Accordingly, it is the
recommendation of this grand jury
that the Board immediately develop a
plan for a reduction in the tax
burden levied on the Liberty County
taxpayer for education as its
foreseeable needs appear to be
already well met.
Members of the grand jury had also
received comments from residents
about the size and appointment of
the new LCBE administration building
which was recently completed at a
cost of approximately $8.2 million.
Additionally, several board members
appearing before the grand jury
stated that while they did see
various versions of the proposed
structure as the design was being
developed, they were unaware of the
cost until the final plans were
presented to them by the Board’s
architect, J. W. Buckley &
Associates, Inc. It was the
consensus of the grand jury members
who toured the administration
building that it was indeed an
elegant structure, but perhaps not
the wisest use of the taxpayers’
money. However, when the grand jury
sent a letter to the Board
requesting information about the
planning and cost associated with
this project, their response clearly
stated that the architects met with
management and every department head
to be housed in the new building on
numerous "intense" planning sessions
centered around both current and
future needs. The Board’s response
also notes that LCBE was always
concerned about cost. It notes that
initial cost estimates were given,
and those cost estimates were
updated, distributed to management
and discussed as changes to the
design and scope of the original
project developed. Finally, the
Board states that the building was
designed to accommodate future
growth, and by designing both common
areas and offices so that they could
be used by multiple individuals and
consolidating departments into one
central space, considerable
classroom space was freed up to be
used for the district’s students.
This grand jury sees two anomalies
in this discussion. First, there
appears to be a substantial lack of
communication between LCBE operating
management and its Board which we
believe is clearly not in the best
interests of a cohesive school
system. Second, it is our opinion
that the Board’s statement
concerning planning for growth made
earlier in this paragraph does not
square completely with the
projections for growth as outlined
in the preceding paragraph in that,
according to the projections about
student population growth made by
the Georgia Capital Outlay Program,
Liberty County’s current facilities
are adequate to accommodate
anticipated student growth for at
least the next five years.
It is
the recommendation of this grand
jury that LCBE management personnel
obtain approval of the Board in the
future before planning significant
capital expenditures in future years
to ensure the cost-effective
expenditure of LCBE financial
resources. Comprehensive cost
estimates of the project should
accompany any proposal.
Liberty County Development
Authority (LCDA)
The Liberty County Development
Authority (LCDA), also known as the
Liberty County Industrial Authority,
was created by the Georgia
legislature in 1958 and implemented
by the Georgia General Assembly in
1964. The Authority has seven
members, two of which are automatic
members by virtue of their office
(Mayor of Hinesville and Chairman of
the Board of Commissioners), and
serve on the LCDA board for as long
as they hold their respective
offices. The County Commission
appoints the four of the remaining
members and the City of Hinesville
appoints the remaining position. The
Chairman of the Authority is Mr.
Allen Brown and the Chief Executive
Officer is Mr. Ronald E. Tolley.
Upon review of information
ultimately obtained from the
Authority in the form of both
written documents and personal
appearances before the grand jury by
its chief executive officer, its
chief financial officer and the
Authority’s attorney, a number of
issues of considerable concern to us
were identified. The more important
ones are included in this
presentment for the consideration of
the taxpayers of Liberty County.
While examining the documents
provided to us by the Authority, we
reviewed a document attached to the
audited financial statement whose
abbreviated name is "OMB Circular
A-133 Compliance Report." This is a
report which must be completed by
the independent certified
accountants generally where the
accounting for grant funds is
required. While the failing outlined
in this document did not impair the
ability of the independent auditors
to give an unqualified opinion as to
the fairness of the presentation of
the Authority’s financial position,
we nevertheless consider the matter
a material failing on the part of
the Authority’s operating personnel.
In March 2005 the Authority was
approved for grant funding by the
Economic Development Authority (EDA)
in the amount of $2,000,000. We
believe that the funds were to be
used in connection with the
construction of the Authority’s
Tradeport East project. Under the
terms of the grant, the Authority
was to submit a Form SF-271 each
month for reimbursement of
authorized construction expenses
incurred during that period.
Authority personnel did not submit
the Forms SF-271 as required, and
over the approximately two year
period required to complete the
work, it used some of its own funds
on hand or money borrowed from other
sources to pay for the work
performed. The auditors state, and
the grand jury agrees, that this
lack of action resulted in
unnecessary interest expense being
incurred by LCDA. In the course of
inquiry, we asked the Authority to
provide us with the number of the
amount of unnecessary interest paid,
and it informed us that the
estimated number was approximately
$22,200. When Ms. Carmen Cole
appeared before the grand jury on
September 5, 2007, she was asked how
this number was derived, and she
informed us that it was an estimate.
It is the opinion of the grand jury
that her estimate is far too low. We
have calculated a number which we
believe that a more representative
interest expense incurred number is
approximately $112,000 as of this
date and continues to accrue. Ms.
Cole also testified that although
the Authority had now spent the
$2,000,000 on the project using
other funds, she believed that this
amount can still be recovered from
the EDA. As of the date of this
presentment, it is our understanding
that all of the filings have still
not been fully accomplished, so
perhaps more important than the
matter of the interest involved
remains the matter of the recovery
by the Authority of the $2,000,000
grant funds.
A far more disturbing issue for the
grand jury is a proposed contract
for the design and construction of a
2 million gallons per day wastewater
treatment facility between the
Authority and CH2MHill, a major
engineering firm based in Colorado.
The proposed facility is to be
located in the vicinity of the
Tradeport East development in
eastern Liberty County, and the cost
of its design and construction is
not to exceed $30 million. The grand
jury has issues with the way in
which the engineering firm was
selected for the work, the type of
contract proposed, the type of
wastewater treatment facility to be
constructed, its size, the proposed
cost, the way it is to be financed,
and the potential financial risks
involved. While this issue has been
and remains a difficult technical
one with which this grand jury has
tried to deal, we will do our best
to explain our concerns in a way
that we hope provides you, the
Liberty County taxpayer, some
insight into the problem.
Because the grand jury only
subpoenaed the minutes of the
Authority for the year 2007, we can
only say with certainty what we know
transpired during that time period.
However, some of the information
contained in the discussion was
obtained from other sources and some
of it is second hand. In spite of
those limitations, we strongly feel
that it should be considered.
In the Authority minutes of February
26, 2007 there appears a discussion
by Mr. Wayne Murphy of the CH2MHill
firm of his opinion on the time
difference required to pursue the
traditional way of building a
wastewater treatment plant (design,
take bids and award, construct)with
what is sometimes referred to as the
"design/build" approach. Under the
"design/build" approach, however,
the engineer and the contractor can
be the same entity or they may be
separate entities, but work begins
on the project before the final
plans and specifications have been
completed. While there may be a
number of reasons why an owner would
select the "design/build" approach
over the traditional one, perhaps
the most common one is that the
project needs to be constructed on a
fast track basis; that is, within a
limited amount of time. A
disadvantage of this method is that
the construction contractor for the
work is also selected from the start
of the project. As a consequence,
the prospect of receiving a more
competitive price when there are a
number of contractors bidding on the
work is lost. In reviewing minutes
referring to the needs of developers
in connection with the time frame
needed to construct facilities at or
in the Tradeport East area, the
grand jury found that one of the
major ones, Midway Holdings, Inc.,
had indicated that it would need
approximately 24 months to secure
the necessary permitting and other
matters before they could begin
vertical construction. However, for
reasons not indicated in the minutes
of April 26, 2007, the Authority
mandated to that group that vertical
construction must begin within 18
months. We can find no justification
for setting what appears to be an
artificial deadline for
construction. We also believe that
because there appeared to be no
overriding reason for an accelerated
construction schedule, more
competitive pricing for the work
would be obtained from contractors
if the traditional design, bid and
award, and construct approach is
used. Upon completion of that
presentation, upon motion duly made
and seconded, a motion to formalize
the approval for "design/build"
given to Mr. Murphy at the February
26, 2007 meeting was unanimously
approved. In the same motion,
SunTrust Bank , which had also been
approved by the Authority in the
February 26, 2007 meeting, was also
formally designated as the financing
agent for the project.
Mr. Murphy (CH2MHill) again spoke to
the Authority on the various
treatment methodologies available
for the proposed wastewater
treatment at the Board meeting of
April 2, 2007. After discussion of
the alternatives, according the
minutes, there was a consensus of
those in attendance that the
"membrane" treatment, as the process
for treatment was called, was the
most desirable choice. However,
because not all board members were
in attendance at that meeting and
the "membrane" treatment was easily
the most expensive alternative,
further consideration of the matter
was deferred until the next
available meeting date. However,
there was apparently a desire by the
board members to keep moving forward
with the project, so on a motion
directing CH2MHill to move forward
toward the membrane treatment design
approach was made by board member
Mr. Arnold and seconded board member
Mr. Ratcliffe. Upon vote, it was
unanimously approved.
The Board next met on April 23, 2007
where the various approaches to
wastewater treatment was again a
significant item on the agenda. At
that meeting Mr. Murphy outlined the
various treatment facility
processing options available
(conventional, sequential batch
reactor, and membrane batch
reactor). He further noted that all
three methods could currently meet
or exceed state discharge standards,
but the sequential batch reactor and
the membrane batch reactor methods
could meet higher standards than the
conventional method, and the
membrane method meet the highest
standards and was the most
environmentally friendly. However,
he also noted that the construction
of a treatment facility using this
method could cost as much as
$10,000,000 or 50 percent more than
the next best method. After
discussion, on a motion was made by
board member Mr. Arnold and seconded
by board member Mr. Smith directing
CH2MHill to move forward with the
design of the new facility using the
membrane batch reactor approach and
authorizing Chairman Mr.Brown to
execute the necessary documents with
SunTrust Bank for the financing of
up to $30,000,000 for construction
of the proposed facility. The motion
passed on a vote of 6-1 with board
member Mr. McIver opposing.
In the state of Georgia it is not
required that a governmental entity
bid work for professional services,
but when a construction contract
exceeds $100,000 in amount, we
believe that solicitation of bidders
is required under state law.
Therefore, because the $30,000,000
amount included construction and was
clearly in excess of that minimum, a
Request for Proposal (RFP) was
required. On April 27, 2007 an RFP
which we believe was prepared in
large part by CH2MHill was,
according to Ms. Cole, the
contracting officer for the project,
posted on the Authority website. It
should also be noted that the scope
of the RFP had been expanded from a
"design/build" to a
"design/build/operate." This was a
significant change, not only because
the Board had voted to award only a
"design/build" effort, but also
because the expansion of the scope
of work to "design/build/operate"
further restricted the number of
potential responders who might know
to look for the RFP on the
Authority’s website. According to
her testimony, the project was not
advertised in any other way. The
deadline for the response to the RFP
was May 28, 2007, subsequently
extended to May 30. According to Ms.
Cole, only one bid was received, and
it was from CH2MHill.
The handling of the RFP was not the
grand jury’s only concern. It was
also concerned that the Authority
would support a plan that, while
achieving the highest standard of
treatment, would cost possibly
$10,000,000 more, or half again as
much as the next most expensive
method which would also easily meet
and exceed current standards. As a
result, we began consulting with
other engineering firms about the
costs and treatment standards
discussed earlier herein. The
numbers cited were largely verified
in that inquiry. However, in the
search for additional information,
we discovered that approximately
five years ago, the Authority had
employed Thomas & Hutton, Inc.,
consulting environmental engineers
in Savannah, Georgia, to prepare a
wastewater master plan for the
Tradeport East area of Liberty
County. That firm prepared the plan
for a fee of $5,000. Their study
recommended the construction of a
conventional or traditional
wastewater treatment facility with a
500,000 gallons per day capacity
which would meet all existing state
discharge requirements and could be
readily expanded. It could be built
at an estimated cost of
approximately $5,000,000. It is also
our understanding that the Authority
recently commissioned CH2MHill to
perform a similar study which
resulted in the treatment plan
already discussed herein. The
CH2MHill fee for that study was
reportedly in the vicinity of
$322,000.
We think that the difference between
a facility costing $5,000,000 and
one costing $30,000,000 is very
substantial, and we believe that the
taxpayers of Liberty County will
agree. However, it should be noted
that there are a number of
differences between the two proposed
facilities. The plan approved by the
Authority provides for the highest
level of waste treatment and would
have four times the treatment
capacity of the Thomas & Hutton plan
which would meet current discharge
standards, but might not meet those
which could be set in the future.
Although it is not probable, it is
possible that the membrane batch
reactor method selected by the
Authority might not meet all future
criteria either.
Yet another very important
consideration in designing a
wastewater treatment facility is the
demand that is expected to be placed
upon it. The proposed treatment
facility is intended to be
constructed in an area that is not
currently served. As a consequence,
there is no immediate demand for
sewer service. Moreover, because of
the nature of the
commercial/industrial customers in
the area and those likely to come
there, those accounts are not
expected to make significant demands
upon the proposed wastewater system.
Demand, therefore, will grow up
largely from the residential
development that should necessarily
follow. A logical question which
follows from that observation is one
of how much residential development
can each of the proposed wastewater
treatment facilities handle?
Assuming average residential water
demand of approximately 300 gallons
per day, a usage figure which
generally approximates the number
accepted by the American Water Works
Association, the Thomas & Hutton
facility could serve perhaps 1,700
homes, while the CH2MHill facility
could serve approximately 6,700
residential customers. However,
because the Thomas & Hutton facility
design plan called for it to be
readily upgradable, it can be
assumed that additional daily
treatment capacity, possibly in
500,000 gallon increments, could be
readily added as its current
capacity was approached, thereby
avoiding the commitment of
additional construction cost funding
until the capacity was actually
needed. Additionally, the
incremental approach to expanding
waste treatment capacity would allow
the engineers the option of
incorporating the then existing best
available technology into the
expanded facility to insure that the
facility was as environmentally
friendly as it was affordable.
Finally, the most important
consideration, we believe, is not
the cost of constructing a proposed
wastewater treatment facility, but
the cost of operating it as the
plant must continue to operate at
least for the length of its design
life. A generally recognized
benchmark in the wastewater
treatment design field is 20 years.
On this point we believe that there
are two very important
considerations. First, we do believe
that if you build it, so to speak,
they will come. We firmly believe
that with waste treatment facilities
available, development will begin to
occur. In the beginning, however, it
will literally be only a trickle at
the wastewater treatment plant, and
that is a problem because to operate
properly, a facility of that type
requires flow through it. If it does
not have adequate flow, which flow
must be supplemented, and it follows
further that the minimum flow
through a 500,000 gallons per day
facility will be less than that for
a 2,000,000 per day capacity.
Additionally, because of the way in
which a membrane batch reactor
facility must process the waste
coming to it, the power consumption
of the pumps required to push or
pull the waste through the membranes
will not be inconsequential.
Moreover, based on discussion with
the consulting engineers with whom
we discussed the matter, the
consensus of opinion was that the
membranes themselves would probably
have to be replaced approximately
every 7 to 9 years. And those
membranes are expensive. Mr. Kelly
Davis, attorney for the Authority,
told the grand jury in his
appearance on September 5 that Mr.
Murphy had told the Board that
replacement of the filter media and
possibly other equipment such as the
pumps could be very expensive,
possibly as high as 50 percent of
the plant construction cost.
Therefore, the possibility exists
that there might not be more than
300 homes constructed per year
(effectively, one home per day), so
the initial capacity need might not
be more than 500,000 gallons per day
would be adequate for at least five
or more years.
To this point the focus of this
discussion has been on which
treatment process would best meet
the needs of the Tradeport East
service area for the amount of money
spent, but there is the equally
important matter of how we are going
to pay for this undertaking as well.
Based on correspondence to the
Authority from the potentially major
developers for that area and the
Authority’s response to them, a
major source of funding was to be
from sewer impact fees collected.
Although the total amount expected
to be obtained from this source is
unknown, based on the data that we
do have, that number could have been
expected to exceed $10,000,000.
Collection of an amount of this size
would significantly reduce the
amount that the Authority would have
to borrow to finance the project.
However, terms relating to payment
of impact fees, as originally
proposed, were deemed so
prohibitive, restrictive and unfair
that at least two of the four
possible major developers have
postponed indefinitely their plans
for projects in the Tradeport East
area, one has apparently developed a
more equitable arrangement with the
City of Midway, and one has said
that she will not deal with the
matter. Instead, she will simply
sell to a developer and not worry
about the problem. Unfortunately for
her, any potential buyer will worry
about the problem, and his or her
concern will be reflected in the
purchase price. The Authority has
subsequently amended its terms for
the payment of impact fees, but this
may well be too little, too late.
Should the $5,000,000 project be
constructed and the developers do
not follow through with their plans,
a load will be placed on the
shoulders of the taxpayers of
Liberty County to amortize that
debt; should the $30,000,000 project
suffer the same fate, we think that
the burden to the taxpayers of
Liberty County could be considerably
greater.
With the considerations
outlined herein in connection with
the proposed wastewater treatment
facility financing in mind, we, the
grand jury offer the following
recommendations in connection with
this endeavor:
- If the contract with
CH2MHill has not yet been
finalized, immediately cease all
efforts to do so. If it has been
finalized, rescind or terminate
it even though it could result
in the payment of a contract
termination fee by the
Authority. While this action
could prove expensive, it will
certainly by less than the $30
million solution currently
proposed.
- The Authority should
immediately contact the City of
Midway to discuss the
availability of capacity at
their waste treatment facility
for its needs. Based on
information in the Authority’s
minutes for the year 2007, the
currently projected treatment
capacity needed by the large
developers with which it has
been dealing is approximately
132,000 gallons per day. The
City of Midway facility is
already permitted by the state
and operational. We do not see
the need to reinvent the wheel
unless the City of Midway has no
interest in entertaining a
reasonable proposal from the
Authority.
- If
an offer by the Authority to the
City of Midway is not
sufficiently attractive to
develop a workable arrangement,
or if the City of Midway does
not want to deal with the
Authority, then the Authority
should then send out Requests
for Proposals to a number of
qualified engineering firms.
There are several of them in the
surrounding counties.
Additionally, because there is
no time constraint on when the
facility must be operational,
the traditional approach; that
is, design the project, take
bids on the construction of the
waste treatment facility, award
the construction contract to the
most responsible, responsive
contractor, and then have the
engineering firm selected for
design oversee the construction
of the facility in conformance
with the plans and
specifications which it prepared
for the project.
- The
waste treatment facility to be
constructed should be designed
so as to be readily expandible
in approximately similar
increments. We do not know what
the optimal increments might be,
but we suspect that additions to
capacity of 500,000 gallons per
day would probably be a
desirable number. The advantages
of designing a facility so that
it could be readily expandable
are many: (1) it saves the
Authority from committing money
for capacity that it might not
need for as much as 20 years;
(2) it enables the plant to
operate at a lower cost because
it will not have to supplement
the wastewater flow that would
be required by a larger plant to
operate efficiently; and (3) the
use of the incremental
expansions approach would enable
the engineers responsible for
the expansion to use the best
available technology existing at
that time to treat the
wastewater coming into the
plant.
- Because there is not a tight
time frame for the construction
of the project, we also
recommend that the proposed
financing arrangement with
SunTrust Bank also be
terminated. Moreover, we are
also very dubious of that bank’s
claim that it would be able to
finance the project at a lower
interest rate than could GEFA
(the Georgia Environmental
Financing Authority) which
normally has the advantage of a
subsidized interest rate.
- Future grand juries should
follow up with the Authority in
their annual reports to ensure
that the $2,000,000 in Economic
Development Authority grant
funds is ultimately recovered
and properly used by it.
Liberty Consolidated Planning
Commission (LCPC)
The Liberty Consolidated
Planning Commission is a
relatively new organization,
arising out of the
consolidation, on January 1,
2005, of staff members from the
Hinesville Metropolitan Planning
Organization, the City of
Hinesville, and Liberty County.
LCPC is led by its director,
H.E. "Sonny" Timmerman, P.E.,
AICP. This entity replaced the
Hinesville Planning and Zoning
Board and the Joint Planning
Commission which handled a
similar function for Liberty
County and the municipalities
other than Hinesville.
Beginning with a staff of five
persons in 2005, LCPC added two
additional employees in 2006,
and plans to be at a level of
ten staff members at the end of
the current business year.
Operating expense data per
employee for 2005 was not
available in the first year of
consolidation which was a
partial operating year, but that
number for 2006 was $130,852 for
a total of $915,964, and for
2007 was $107,483for a total of
$1,074,830. Nevertheless, the
2007 total budget was up
substantially in total dollars
even though the per capita
number decrease due to the
sizeable increase in the number
of staff members. A significant
portion of the 2007 operating
expense was attributable to
outside engineering and other
professional services for
specific projects, so the budget
for this agency should decrease
by the cost of those services
when those projects have been
completed. We also recognize
that the duties of that agency
are still evolving somewhat, but
we have requested that it report
to the grand jury both in total
operating budget and on a per
employee basis in the future to
give that body one possible
benchmark to measure what it is
costing Liberty County to
provide this service. Like many
governmental agencies, LCPC is
able to carry out some parts of
its mission as a result of grant
funding obtained. However, we
cautioned that agency to be
mindful that when considering
the expansion of staff, grants
should not be viewed as a
permanent source of funding
because there is no guarantee
that they will be available in
future years, and the residents
of Liberty County already have a
very substantial tax burden that
does not need to be expanded.
By
the time the next grand jury is
impaneled, LCPC should have
evolved substantially in form
and operation so that its role
can be more clearly defined and
evaluated. A brief summary
report on its operations for its
most recently completed fiscal
(business) year should be
available for it.
Liberty County Board of
Commissioners (LCBC)
The Liberty County Board of
Commissioners provides an
extensive range of services
including, but not limited to,
county law enforcement, rural
fire protection, construction
and maintenance of highways,
streets and other
infrastructure, recreational and
cultural development programs,
health and welfare programs,
indigent care assistance, solid
waste services and other
essential community services.
The county operates under the
commission-administrator form of
government, and the chief
executive officer for LCBC is
Joseph W. Brown, County
Administrator.
Much of the information which we
were seeking was provided to us
in the report presented to us by
Mr. Brown’s office. We did,
however, question the projected
figure of $20.6 billion economic
impact figure for the Mid-Coast
Business Center which was cited
in the Commissioner’s
Management’s Discussion and
Analysis section included with
its audit for the fiscal year
ended June 30, 2006. Upon
further analysis, it was
determined that this information
had been provided to them by the
Liberty County Development
Authority, and it was the
projected number for the
ultimate development of the
entire Coastal Georgia Mega-Park
project, not the Mid-Coast
Business Center itself.
The grand jury expressed concern
that information in that report
appeared to indicate a
substantial reliance on grant
funding for both ongoing and
capital needs. The County’s
financial officer, Ms. Kimberly
McGlothlin, responded to our
concern in a letter dated July
23, 2007 by noting that Liberty
County had six significant
operating grants, two
significant capital grants, and
several smaller capital grants.
She noted that prior to the
acceptance of any capital
project, the various funding
sources are always identified,
so those projects should not
prove to be a funding problem.
However, she also noted that
where operating grants are
concerned, they are applied for
on an annual basis. As a
consequence, should the grants
not be awarded, then it would be
up to the Board of Commissioners
to appropriate funds for the
continued operation of the
affected programs.
The grand jury also expressed
concern in a letter to Mr. Brown
about a number of operating
entities within the county which
appeared to require a continuous
subsidy by it. Among them were
the Solid Waste Authority, the
Liberty Regional Medical Center,
and the E-911 Emergency System.
Ms. McGlothlin went into
considerable detail on the
progress made by the Solid Waste
Authority toward the achievement
of self-sustaining financial
status, but she expressed some
doubt that the county would ever
be able to recover earlier
operating losses that it had
underwritten. She was,
nevertheless, optimistic about
the financial soundness of the
operation of the Solid Waste
Authority in future years.
On the matter of the Liberty
Regional Medical Center she was
not as optimistic. She noted
that it is a component unit of
Liberty County, and as such it
undergoes a separate independent
audit, information is taken from
that audit and included in part
of Liberty County’s annual
financial report. Summary
information available from
Liberty County indicated Liberty
Regional Medical Center has not
been profitable in recent years
and possibly since its
inception, but the grand jury
did not have the time to go
further into the analysis of the
operation of that entity, and
there is some question as to
whether it had the authority to
pursue the matter further. The
grand jury believes that this
matter should, nevertheless, be
of concern to the citizens of
Liberty County because, as Ms.
McGlothlin notes, the
relationship between the
hospital and the Board of
Commissioners is significant due
to the fact that the
Commissioners level an annual
millage rate on behalf of the
hospital.
On the E-911 Emergency System
Ms. McGlothlin noted that this
fund was a special revenue fund
and not self-sustaining, and she
did not believe that it would
ever be so. Fees collected from
both land lines and mobile
telephones are not nearly enough
to support this operation, and
the Commissioners have no plans
at this time to make it so by
means of an assessment or
increased fees. It will continue
to be supplemented by an annual
operating transfer from the
General Fund.
Finally, Ms. McGlothlin noted
that the annual reporting format
suggested by the grand jury for
the other agencies which must
report to it would not fit LCBC
because its operations were so
varied and extensive. We believe
that the financial information
provided from its audit along
with the information in its
Management’s Discussion and
Analysis section, provides
adequate financial information
for its purposes.
Dr. Glenn Carter & Liberty
County Hospital Authority
On July 11, 2007 Dr. Carter
appeared before this grand jury
to ask for our assistance in
resolving his differences with
the Liberty County Hospital
Authority ("the Authority"). He
explained to the grand jury that
approximately four years
earlier, his privileges to
practice at Liberty Memorial
Hospital had been suspended. He
stated that he appealed this
decision by that entity and an
independent review board
consisting of individuals
selected by the Liberty County
Hospital Authority to review the
matter was convened to review
the Authority’s decision.
According to Dr. Carter, the
unanimous recommendation of the
review board was his practicing
privileges at that facility
should be immediately
reinstated, but the Authority
rejected the review board’s
finding and continued to deny
him access to that facility.
Dr. Carter further states that
at this point he had no choice
other than to file suit against
the Authority, and that is where
the matter stands as of the date
of this presentment. He wishes
to make it known that he would
be willing to terminate his suit
against the Authority if some
acceptable resolution of this
dispute could be achieved. He
additionally noted that the
practice constraint was not only
unfair to him, in his opinion,
but it was also unfair to the
thousands of his patients who
are residents and taxpayers in
Liberty County because they pay
taxes to support the operation
of the hospital and should, as a
result, have the right to be
treated by their physician at
that facility.
The grand jury then asked Dr.
Carter to provide more specific
information on the issues
leading to the dispute, and he
explained that he had been
accused by the Authority of
providing improper treatment of
six patients that he had placed
in that facility for treatment.
To provide more detail to the
grand jury, Dr. Carter discussed
the comprehensive treatment of
one of cases in question, noting
that he had treated that patient
for years and had full knowledge
of his/her medical history.
Finally, Dr. Carter noted that
while two of the six patients
are no longer living, the
remaining four continued to use
his after the initiation of the
dispute, and several are still
patients of him as of this date.
The grand jury then thanked him
for his testimony and excused
him.
The grand jury then deliberated
the case based on this
information and a presentation
by the Authority to a previous
grand jury, but it was
subsequently advised by Judge
Rahn that it was his belief that
nothing further could be
achieved as the issue was now in
litigation, and we could not
access the pertinent files for
further consideration. The grand
jury determined that further
inquiry was fruitless.
To the extent that the grand
jury is permitted to offer an
opinion on this matter, it
strongly encourages the parties
to the dispute mediate their
differences, if at all possible,
with the assistance of the Board
of Commissioners if necessary to
ensure that the affected
taxpayer/patients are able to
readily access hospital
facilities here in Liberty
County to receive timely
treatment from their qualified
physician.
It
is our recommendation that
unless it can be firmly
established that Dr. Carter was
guilty of conduct that was
illegal, unethical or immoral to
a degree that would cause his
license to practice to be
revoked by the State of Georgia,
his privilege to practice at the
Authority’s facility here in
Liberty County be reinstated as
soon as possible.
Conclusion
In closing these presentments,
we the 2007 Liberty County Grand
Jury, hope that the effort that
we have put forth in what we
believe is in the best interests
of our citizen-taxpayers will
provide a starting point for
future grand juries which they
can use to assess the
performance of the entities
which exist to serve them. It is
not our task to provide
responsible direction for the
agencies reviewed herein; their
own officers are civic leaders
charged with that obligation. It
is, however, the duty of this
and all future grand juries to
monitor that performance and
report to you, the taxpayer, on
how well we believe that this
had been done. This is our
report to you.
Members of the 2007 Liberty
County Grand Jury:
Paul B. Krebs, Jr., Foreman
William F. Goodwin, Vice Foreman
Beverly M. Childs, Clerk
John W. Stetzer, Jr., Assistant
Clerk
Franklin D. Bradford
Diane Kroell
Juan R. Colon
Dolores S. Mitchell
Lamar T. Cook
Jose A. Ortiz
Maria J. Crowe
Charlene D. Rocker
Debra Frazier
Lamar Speight
Pijit P. Healy
Cato Walthour, Jr.
Tom Holmes III
Maria C. Winnubst
Oralia Jiminez
Mary E. Woods